07-05-2021

Apo Agua Infrastructura, Inc. and the Davao City Water District (DCWD) reported that they had completed the Davao Bulk Water Supply Project’s Conveyance and Penstock Pipeline. The pipeline will deliver water from their Weir to their Water Treatment Plant. Mr. Ramon “Shake” Aboitiz Tuason, Operational Head of Apo Agua Infrastructura Inc, and Engr. Christine Guarde, Division Manager of DCWD Engineering Department, also reported that they also started road restoration works along the highways. Apo Agua proudly stated that 51% of their workforce is sourced from the host barangays of the project, namely, Carmen, Cadalian, Tawan-Tawan, Baguio, Wines, Tamugan, and Tambobong. They are targeting the first drop of water by the end of 2021.